PROJECT TIMELINE
Grant Submittal, Phase I – August 2020
Grant award, Phase I – November 2020
Phase I Permitting – Summer 2021
Phase I Design – Fall of 2021
Phase I Project Bid – early spring 2022
Phase I Construction – spring/summer of 2022
Four to Six Additional Design/Construction Phases – 5 to 10 years desired, pending funding